Python Library API

The ccpm_scheduler Python package exposes a pure Python library API for loading, validating, building, verifying, and visualizing CCPM schedules programmatically.

from ccpm_scheduler import (
    load_network,
    validate_network,
    build_schedule,
    check_schedule,
    plot_schedule,
    write_network_html,
)

# 1. Load network
network = load_network("tasks.csv", "resources.csv", "calendar.csv")

# 2. Validate network
report = validate_network(network)
if report.ok:
    # 3. Build schedule
    result = build_schedule(network, title="Website Relaunch", buffer_method="cap")

    # 4. Verify schedule
    assert check_schedule(result.schedule, network).ok

    # 5. Render outputs
    plot_schedule(result.schedule, "gantt.png", resources=network.resources)
    write_network_html(result.schedule, "network.html", title="Website Relaunch")

Core Pipeline Functions

load_network(tasks_path, resources_path, calendar_path=None) -> Network

Loads a project network from CSV files into a typed Network model.

network_from_json(json_str_or_dict) -> Network

Parses a JSON string or dict in the unified exchange format into a typed Network model.

network_to_json(network: Network) -> dict

Serializes a Network instance into the unified JSON exchange dictionary.

validate_network(network: Network) -> ValidationReport

Validates network logic and returns a ValidationReport containing structured Issue records. Does not raise exceptions on invalid networks; check report.ok or report.errors.

build_schedule(network: Network, title: str = "CCPM schedule", buffer_method: str = "cap") -> BuildResult

Executes resource leveling, late-start scheduling, Critical Chain identification, and buffer sizing. Returns a BuildResult dataclass containing schedule, summary_markdown, title, and stats.

check_schedule(schedule: Schedule, network: Network) -> ValidationReport

Re-verifies an existing Schedule object against its source Network. Returns a ValidationReport with any structural or resource capacity violations found.

plot_schedule(schedule, out_path, title=..., resources=..., calendar=...)

Renders a buffer-aware Gantt chart PNG image. Matplotlib is loaded lazily only when this function is invoked.

write_network_html(schedule, out_path, title=..., tasks=...)

Writes an interactive HTML dependency graph using embedded data and vis-network.


Key Data Models

Task

Dataclass representing one project task. - id: str - name: str | None - realistic_duration: object (working days estimate with safety) - optimal_duration: object (padding-free working days estimate) - links: list[Link] (predecessor links) - resource_ids: list[str] (assigned resources)

Resource

  • id: str
  • name: str | None
  • capacity: object (integer capacity per day, default 1)

ValidationReport

  • ok: bool: True if there are zero errors (warnings are permitted).
  • issues: list[Issue]: List of all validation issues.
  • errors: list[Issue]: Filtered list of issues where severity == "error".
  • warnings: list[Issue]: Filtered list of issues where severity == "warning".
  • start_tasks: list[str]: Task IDs with no predecessors.
  • terminal_tasks: list[str]: Task IDs with no successors.

Issue

  • code: str: Machine-readable error or warning code.
  • severity: str: "error" or "warning".
  • message: str: Human-readable explanation.
  • task_ids: tuple[str, ...]: Offending task IDs.
  • resource_ids: tuple[str, ...]: Offending resource IDs.

Machine-Readable Validation Codes

When embedding ccpm-scheduler into custom UIs or agent applications, inspect Issue.code to surface structured errors:

Code Severity Description
E_DUP_TASK Error Duplicate task ID found in network.
E_DUP_RESOURCE Error Duplicate resource ID found in network.
E_UNKNOWN_PRED Error Task references a predecessor ID that does not exist.
E_MALFORMED_LINK Error Predecessor link syntax is invalid (e.g. A:XX).
E_CYCLE Error Circular dependency detected (cycle path provided in message).
E_BAD_DURATION Error Task duration is non-numeric or negative (< 0). 0 is allowed — it marks a milestone task.
E_FRACTIONAL_DURATION Error Task duration is fractional (v1 requires integer working days).
E_FRACTIONAL_CAPACITY Error Resource capacity is fractional (v1 requires integer units).
E_BAD_ALLOCATION Error Task's per-resource allocation (units of that resource's daily capacity consumed) is non-numeric or <= 0.
E_ALLOCATION_EXCEEDS_CAPACITY Error Task's allocation of a resource exceeds that resource's own capacity — unsatisfiable even alone.
E_NO_RESOURCE Error Task has no resources assigned (cannot contend for leveling). Exempt for a duration-0 milestone task.
E_UNKNOWN_RESOURCE Error Task assigned to a resource ID not listed in resources.
E_BAD_CAPACITY Error Resource capacity is less than 1 (< 1).
E_CAL_BAD_ROW Error Calendar window contains unparseable values.
E_CAL_UNKNOWN_RESOURCE Error Calendar window targets unknown resource ID.
E_CAL_EMPTY_RANGE Error Calendar window from >= to.
E_CAL_NEG_CAPACITY Error Calendar window capacity is less than 0 (< 0).
E_CAL_OVERLAP Error Overlapping calendar windows for the same resource.
W_CAPACITY_GT1 Warning Resource capacity is greater than 1 (> 1) — a pooled resource, shared across concurrent tasks or units within one task.
W_NON_FS_LINK Warning Non-Finish-to-Start link used (SS, FF, SF).
W_LEGACY_COLUMNS Warning Input CSV uses legacy column names (predecessors/resources instead of predecessor_ids/resource_ids).

These are validate_network's own codes. check_schedule re-verifies a produced schedule against its source network and reports its own separate set of codes (e.g. E_ARITHMETIC, E_LINK_VIOLATION, E_OVERLOAD, E_PB_COUNT, E_DISCONNECTED_TASK) — see the check.py module docstring for the full list.