Buffer sizing methods

How the project buffer and each feeding buffer get their size. The placement of buffers (critical chain identification, merge points, gap handling) is method-independent and described in the README; this page covers only the sizing arithmetic, the three supported methods, and how each behaves when task estimates are two-point, single-point, or a mixture.

Why offer more than one method? No sizing formula is "correct" — the research literature has argued for decades without settling it. The real benefit of CCPM buffers is behavioral: a pooled, visible protection that focuses execution attention on the tasks that threaten the promise date. A team that rejects the plan because the buffer formula feels arbitrary never gets those benefits. Offering the standard methods (and defaulting to the most explainable one) removes an adoption obstacle; the buffer can always be manually resized in our-planner before a project enters execution.

Estimate normalization (shared by every method)

Each task carries up to two estimates:

  • realistic_duration — the safe estimate, safety included (what people naturally give).
  • optimal_duration — the aggressive / padding-free estimate (≈ 50% confidence).

Before any buffer arithmetic, every task is normalized to a triple (optimal, realistic, Δ):

Estimates given optimal realistic Δ (safety)
both as given as given realistic − optimal
realistic only ⌈realistic / 2⌉ (the classic 50% cut) as given realistic − ⌈realistic/2⌉
optimal only as given 2 × optimal (derived, inverse of the cut) optimal

Tasks are always scheduled at their optimal duration regardless of method — the methods differ only in how Δ (or chain length) is aggregated into a buffer. In a mixed network the normalization is per-task, so two-point tasks contribute their stated safety and single-point tasks contribute a derived (mechanical 50%) safety to the same sum.

Mixed-network caveat: CAP and RSEM are only as informative as the Δs they aggregate. When most Δs are derived rather than estimated, both methods degrade toward mechanical 50% assumptions — the summary should report how many tasks in each protected chain had derived estimates, so the user knows how much to trust the number.

Buffers protect a chain: the critical chain for the project buffer, the feeding chain (or, for extra merge edges, the feeder's backward non-critical closure) for a feeding buffer. In the formulas below, sums run over the tasks of the protected chain. All results round up (ceil); zero-length feeding buffers are never emitted (the merge is flagged unprotected instead).

The methods

CAP — Cut & Paste (default)

Buffer = Σ Δᵢ

Goldratt's original method: every estimate contains embedded safety; remove it from each task (schedule at optimal) and paste the sum of what was removed after the chain as the buffer.

  • Two-point estimates: the buffer is exactly the safety the team said their tasks carried, pooled. Promise date = optimal chain + Σ Δ.
  • Single-point (realistic only): Δᵢ ≈ 50% of each task, so the buffer roughly equals the scheduled chain length, and the promise date lands back at the original realistic chain length — same date a traditional plan would promise, but with all protection pooled and visible instead of hidden inside tasks.
  • Mixed: stated Δs and derived Δs sum together; the more two-point estimates, the more the buffer reflects real per-task uncertainty.

Pros: trivially explainable ("we didn't delete your safety — we pooled it"), which is why it is the default: teams new to CCPM can verify the arithmetic against their own estimates. Respects per-task uncertainty. Never under-protects relative to what the team estimated. Cons: grows linearly with chain length — no statistical aggregation benefit, so long chains are over-protected (the promise date gives back everything the cut gained). Plans look no shorter than traditional ones (only the behavior differs).

HCHAIN — 50% of chain length

Buffer = ⌈0.5 × Σ optimalᵢ⌉

The most common textbook rule: the buffer is half the protected chain's scheduled length.

  • Two-point estimates: Δs are ignored — a chain of tight estimates and a chain of wild guesses of equal length get identical buffers. This is the method's central weakness: it treats every task as equally uncertain.
  • Single-point: with optimal derived as realistic/2, the buffer is ~25% of the realistic chain, and the promise date lands at ~75% of the traditional plan length.
  • Mixed: only the optimal durations matter; the estimate mix changes nothing.

Pros: dead simple; produces visibly shorter plans (~75% of traditional), which sells CCPM's schedule-compression story; buffer scales with chain length so it never vanishes. Cons: ignores all uncertainty information (the user-visible symptom that motivated alternatives); still linear in chain length, so statistically over-protects long chains while potentially under-protecting short chains of high-variance tasks.

RSEM — Root-Squared Error Method

Buffer = ⌈√(Σ Δᵢ²)⌉

Treats each task's Δ as ~2 standard deviations of its duration uncertainty and pools independent uncertainties the statistical way: the buffer is the root of the summed squares (equivalently 2·√(Σ(Δᵢ/2)²)). See the PM Knowledge Center description.

  • Two-point estimates: the intended use — the buffer grows with √n rather than n, so long chains are not over-protected the way CAP/HCHAIN over-protect them.
  • Single-point: Δᵢ = derived 50% cuts, so the formula runs on mechanical inputs — the result is a √n-scaled version of CAP with no real information gain. Usable, but the caveat above applies in full.
  • Mixed: works per the normalization; derived-Δ tasks dilute the statistical meaning.

Pros: statistically grounded aggregation; per-task uncertainty matters; long chains get proportionally smaller (cheaper) buffers. Cons: assumes task uncertainties are independent — correlated risks (same person, same unknown technology) make it under-protect; small task counts produce buffers that can feel alarmingly thin to newcomers; hardest of the three to explain.

Worked example

A critical chain of four tasks, two estimated two-point, two single-point:

Task realistic optimal Δ note
A 10 6 4 stated
B 20 10 10 stated
C 10 (5) 5 derived: ⌈10/2⌉
D 20 (10) 10 derived: ⌈20/2⌉

Scheduled (optimal) chain = 31 days; traditional (realistic) plan = 60 days.

Method Buffer Promise date
CAP 4+10+5+10 = 29 day 60 (= the traditional plan, protection pooled)
HCHAIN ⌈0.5 × 31⌉ = 16 day 47
RSEM ⌈√(4²+10²+5²+10²)⌉ = ⌈√241⌉ = 16 day 47

The HCHAIN/RSEM tie here is a coincidence of the numbers. The scaling difference shows on uniform chains — n tasks, each optimal 5, Δ 5:

n CAP HCHAIN RSEM
2 10 5 8
6 30 15 13

RSEM out-buffers HCHAIN on short chains and under-buffers it on long ones — that is the √n aggregation at work.

Selecting a method

  • CLI: ccpm-scheduler build ... --buffer-method {cap,hchain,rsem} — default cap.

  • Library: build_schedule(network, title, buffer_method="cap"). The JSON exchange format accepts a top-level "buffer_method" key, which an explicit flag/argument overrides.

  • The chosen method is recorded in summary.md, along with how many tasks in each protected chain had derived Δs; feeding and project buffers always use the same method within one schedule. A buffer is never smaller than 1 day. When a feeding chain cannot shift far enough to fit its full buffer, the achieved gap is all the protection that merge has — the summary shows N (method wanted M) so the shortfall is visible.
  • Consumers: our-planner sets the method per project (CCPM Method in its project settings); the AI skill asks the user, and when the user is unsure it gathers two-point estimates and uses CAP.

  • Whatever the method produces, buffers can be manually resized in our-planner before the project enters execution mode — the formula is a starting point, not a contract.


Frequently Asked Questions (FAQ)

How does ccpm-scheduler deal with feeding buffers when feeding chains are equally long as (or land tight against) the Critical Chain?

When a feeding chain finishes tight against its merge point on the Critical Chain (or when project start / resource constraints prevent shifting the feeding chain earlier), attempting to force a full-sized feeding buffer could risk elongating the Critical Chain or pushing project start before Day 0.

ccpm-scheduler resolves this using constrained backward shifting, gap absorption (pre-consumed buffers), and unprotected merge detection:

  1. Constrained Backward Shifting: The scheduler first attempts to shift the feeding chain backward to open up space for the calculated feeding buffer size \(M\), bounded by Day 0, predecessor links, and resource availability across all chains.
  2. Pre-Consumed Buffers & Gap Absorption (N (method wanted M)): If the feeding chain cannot shift far enough to fit the full calculated buffer \(M\), ccpm-scheduler fits whatever gap \(N\) is available (\(0 < N < M\)). It sets the buffer duration to \(N\) days without extending the Critical Chain, and reports N (method wanted M) in summary.md and CLI build stats so the buffer shortfall is fully visible.
  3. Unprotected Merges (gap = 0): If the feeding chain finishes tight against its critical successor (\(N = 0\)) and cannot shift earlier at all, ccpm-scheduler enforces a policy to never emit a zero-length (0-day) buffer row. The buffer is omitted entirely and flagged in summary.md with an explicit warning:

    "Warning: the merge ... has no room for a feeding buffer — that path is effectively critical. Watch it as closely as the critical chain."

See the full FAQ page for more answers to common scheduling and layout questions.