Sample Portfolio Walkthrough

sample-app-file/realistic-portfolio.json is a generated example file — a whole organisation's project portfolio, built to be opened and explored rather than just read about. Where the User Guide documents individual features, this page walks through one realistic file feature by feature, so you can see how the pieces fit together: CCPM scheduling, buffer consumption, full-kit readiness, resource loading, and the reports that sit on top of all of it.

It's also a good file to hand to someone else — a colleague, a client, an audience at a demo — so they can click around a portfolio that already has a story in it, instead of an empty grid.

Open it

File → Open... and pick sample-app-file/realistic-portfolio.json from the repository. It's a plain save file — nothing else to set up.

What it models

An organisation of 30 people (dev, qa, designer, ba, devops, lead, architect, and data specialists), each represented as a named resource tagged with their role, running a portfolio spanning roughly three months in the past through one month ahead of today. Two kinds of work coexist on the same canvas, sharing the same 30-person resource pool — the way a real portfolio actually competes for the same people:

  • 19 mini-projects, each a small rolling-wave network (small/medium/ large shapes — Analysis/Build/Test/Deploy and variants) scheduled for real through Network → Schedule with CCPM..., with a team kept constant for the life of the project. Buffer sizes, the critical chain, and the feeding-buffer merge points are all genuine scheduler output, not hand-picked numbers.
  • One "Ad-hoc / Backlog Work" project — about a quarter of the portfolio's total task volume, tagged backlog plus a priority (P1/P2/P3), pulled from the roster independent of any project team, and deliberately never run through CCPM scheduling. This is the other half of the operating model the mini-projects assume: triage work into a small CCPM-scheduled project, or leave it on the backlog to be pulled by priority.

Because generation is anchored to whenever it was last run, some of the 19 mini-projects land in the past (already complete), some straddle today (in progress), and a few haven't started yet — a realistic mix of every project phase existing on the canvas simultaneously, exactly like a real portfolio.

Task colours: a team convention, not a status

Every task on the grid is filled with whatever colour this file gave it — color is a free-form field, and the app never assigns or changes it on its own. This sample uses one convention, by role:

ROLE_COLOR = {
    'dev': 'LightBlue',
    'qa': 'LightGreen',
    'designer': 'MediumOrchid',
    'ba': 'Khaki',
    'devops': 'Orange',
    'lead': 'Gold',
    'architect': 'CornflowerBlue',
    'data': 'LightSalmon',
}

(sample-app-file/generate_sample_app_file.py). Every mini-project task is coloured by the role of the person assigned to it, and every backlog task is a flat LightYellow regardless of who's on it — so scanning the grid answers "who's doing what kind of work across the whole portfolio right now", the same lens a resource manager needs when deciding whether the org has enough of a given skill committed versus free.

This is genuinely a decision your team has to make, not something the app assumes for you — colour-by-role is only one workable convention. Colour-by-project (so a team can pick its own work out from a shared, multi-project canvas at a glance) or colour-by-priority for a backlog-heavy team are just as valid; whichever is chosen, it's worth writing down and agreeing once, since nothing enforces consistency automatically - Right-click a task → Edit Task Color sets it per task, and it's easy for a convention to quietly drift once several people are creating tasks.

Two things colour does not signal here, worth agreeing on explicitly since they're easy to assume by default:

  • Completion isn't a colour. A done task keeps its role colour - the box fill is deliberately left untouched by state. What does change is the small background rectangle directly behind the task's id/description text: light green for done, dark grey for buffered, both easy to miss at a glance next to a bright role colour. The clearer at-a-glance "how much of this is actually finished" signal is the progress stripe along the bottom edge of the box instead.
  • Chain membership isn't a colour either - that's the thin stripe along the top edge of a task (a chain's own assigned colour, set when it's created), independent of both role colour and state.

Fever charts: where the safety actually went

CCPM strips safety out of individual task estimates and pools it into project/feeding buffers instead, so a task running long shouldn't show up as a blown task date — it should show up as buffer consumption. Open Reports → Fever Chart on a few of the completed projects and compare:

  • Customer Portal Refresh's first feeding buffer finishes deep in the red zone (consumption around 300% of its own baseline) — several tasks feeding into that merge point ran long, and the buffer that was supposed to absorb it wasn't big enough to fully cover the overrun.
  • Returns Workflow's project buffer, by contrast, finishes comfortably in the green (negative consumption — it finished ahead) — its chain ran close enough to plan that the buffer barely got touched.
  • Loyalty Programme Revamp's project buffer is the sharpest story of the three: it tracks green through the first half of the chain, then a run of tasks going badly wrong mid-project drives it straight through yellow into red, finishing with the buffer completely exhausted — consumption past 100% of baseline, meaning this project would genuinely have missed its promised date without the buffer's early warning prompting an intervention. That sharp green-to-red jump partway across the chart, rather than a gradual drift, is itself worth noticing — it's usually a sign of one correlated cause (the generator models this as a "troubled" project, where most of that project's tasks ran long together) rather than ordinary task-by-task noise.

Same organisation, same estimating discipline, genuinely different outcomes — which is the point of tracking it per-project rather than assuming one number describes the whole portfolio.

Toggle Show Status Update Reasons/Notes on the fever chart to see why: every recorded status update in this file carries a reason (On Time, Task Variability, Waiting for Resource, Parkinson's Law, Multitasking, Unplanned Events, Other / Unexplained), the same fixed list a real user picks from in Record Remaining Duration.... Reports → Status Update Log... lists every recorded update for a project in one place if you want to see the full trail rather than just the annotated points on the chart.

Full-Kit Readiness: catching trouble before it starts

The three mini-projects that haven't started yet (still in planning phase) are the interesting case for Reports → Full-Kit Readiness... — unlike fever charts, full-kit readiness matters before execution begins, not just during it.

Open the report for whichever of the three not-yet-started projects has the lowest readiness percentage. You'll typically see something like: the first task (discovery/analysis) and the later QA/deploy tasks already have a full-kit date — that kind of task only needs information known at planning time (requirements, environment, a runbook), so a well-run project gets it done well ahead of the kickoff. The design/build tasks in between, though, show Not Kitted — they genuinely need their own predecessor's actual output (the discovery findings, the agreed design) before there's anything real to kit, so they can't have been finished yet.

That's the distinction this report exists to surface: some gaps are just "still waiting on upstream work, as expected"; others are "this should have been sorted out by now and wasn't" — missing-but-predictable dependencies discovered mid-execution are one of the most common causes of a project grinding to a halt partway through. The report doesn't decide which is which for you, but it puts every task's status in one place so you can.

Resource Over-Allocation: is this actually a problem?

Reports → Resource Over-Allocation... aggregates load across every project a resource (or a tag/role) is committed to — not just whatever's currently on screen — which is exactly the kind of clash a single project's own grid can't show you.

Switch to By Resource and look for Ben Carter — he's double-booked at 200% of capacity for a couple of days in August, drawn from two different projects. Expand the finding and the drill-down shows why it's not necessarily urgent: one of the two tasks (Build-A, in Pricing Engine Update) is on that project's Critical chain, but the other (Build-B, in Contract Renewal Tool) is on a Feeding chain — which by definition has slack absorbing exactly this kind of clash. This is the judgement call the report is built for: a critical-chain/critical-chain clash needs a decision (shift a task, reassign a resource); a critical/feeding clash usually doesn't, because the feeding buffer is already there to absorb it.

Switch to By Tag and you'll typically see the same clashes reappear, aggregated by role instead of by name — in this file no role is saturated in aggregate even though individual people are double-booked, which is itself worth noticing: a tag-level view exists for the opposite case, where three developers are each individually under capacity but the role as a whole is genuinely over-committed, something no single resource's row would ever show as red.

Ben Carter's double-booking exists here because both mini-projects were scheduled independently, each unaware of the other's claim on him — this file predates Account for capacity already committed to other projects, the option now offered by Network → Schedule with CCPM... (see User Guide → Scheduling with CCPM). Re-scheduling either project with that option checked would reduce his exported capacity by the other project's load over the clashing days, pushing the lower-priority task out rather than leaving both projects planned against the same person at the same time — the report above still matters for judging clashes across projects that were scheduled separately (or where a resource's other commitment isn't itself a CCPM-scheduled project), but a single project's own scheduling run can now avoid creating this particular kind of clash in the first place.

Filtering resources by tag when assigning

This file names every resource after a real person (capacity=1.0) and tags them with their skill (ba, dev, qa, designer, devops, lead, architect, data) — one of two ways our-planner can model a resource; the other is a named role resource with capacity set above 1 (e.g. a pooled Developers resource at capacity 3), which this file doesn't currently use.

Right-click any task → Edit Task Resources and try the tag combobox next to the search box — filter to qa, for instance, to narrow the available list down to just the testers, then combine it with a name search. It's scoped to this one dialog deliberately: whether a resource ends up over-allocated once assigned is a question for the Resource Over-Allocation report above, not something this dialog checks live — the positions here are still provisional until a CCPM schedule run actually levels them.

Regenerating the file

sample-app-file/generate_sample_app_file.py builds this file from scratch (uv run python sample-app-file/generate_sample_app_file.py) — a fixed RNG seed keeps the story consistent run to run, but the exact numbers above will drift slightly each time it's regenerated, since the three-month lookback window is always anchored to whichever day it was generated on. The shape of the walkthrough — some projects deep in the red (occasionally a project buffer completely exhausted), some comfortably green, a few not-yet-started projects with partial full-kit readiness, at least one resource double-booked across projects — is what the generator is designed to reproduce, not the specific numbers quoted here.